Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 23 Topic 3 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 23 Topic 3 Discussion

CAPM Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?


A.

One


B.

Five


C.

Six


D.

Seven


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.