New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 29 Topic 3 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 29 Topic 3 Discussion

CAPM Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

Inputs to the Plan Schedule Management process include:


A.

Organizational process assets and the project charter,


B.

Enterprise environmental factors and schedule tools.


C.

Time tables and Pareto diagrams.


D.

Activity attributes and resource calendars.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.