Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 29 Topic 3 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 29 Topic 3 Discussion

CAPM Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

Who determines which dependencies are mandatory during the Sequence Activities process?


A.

Project manager


B.

External stakeholders


C.

Internal stakeholders


D.

Project team


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.