Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 542 Topic 55 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 542 Topic 55 Discussion

PMP Exam Topic 55 Question 542 Discussion:
Question #: 542
Topic #: 55

A project manager needs the team to define the steps and identify the risks of migrating data to a new system.

What type of leadership should the project manager use to accomplish this?


A.

Laissez-faire


B.

Transformational


C.

Dynamic


D.

Servant


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.