Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 542 Topic 55 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 542 Topic 55 Discussion

PMP Exam Topic 55 Question 542 Discussion:
Question #: 542
Topic #: 55

A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.

What should the project manager do?


A.

Create a training schedule for the new team member to follow over the next few weeks.


B.

Escalate the inquiry to the team member's functional manager.


C.

Clarify the relevance of reviewing the documentation on the intranet.


D.

Ask a senior team member to help the new team member navigate through all the documentation.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.