PMI Project Management Professional (2025 Version) PMP Question # 542 Topic 55 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 542 Topic 55 Discussion

PMP Exam Topic 55 Question 542 Discussion:
Question #: 542
Topic #: 55

A project manager has been assigned to a project that is in progress. The project

manager is looking for information regarding why the project is being completed.

What should the project manager do first?


A.

Evaluate the project exit criteria in the project charter.


B.

Reach out to the senior executive sponsor for the project.


C.

Understand the project success criteria and objectives.


D.

Review the project status reporting for the latest information.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.