PMI Project Management Professional (2025 Version) PMP Question # 547 Topic 55 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 547 Topic 55 Discussion

PMP Exam Topic 55 Question 547 Discussion:
Question #: 547
Topic #: 55

During project execution, an important stakeholder threatens to withdraw support

for the project, citing a lack of transparency and accountability in the way the project is being

executed. What should the project manager do to handle this situation?


A.

Approach the stakeholder to address the concerns.


B.

Consult the risk management plan.


C.

Escalate the issue to the project management office (PMO).


D.

Refer the stakeholder to the project sponsor.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.