Questions # 501:

At the end of planning a new project, the project manager needs to schedule the

kick-off meeting but is having difficulty finding a common time slot when all necessary

stakeholders can be available onsite. How should the project manager proceed to

schedule the kick-off meeting?

Options:

A.

Email all stakeholders with the objectives of the project and ask for feedback.


B.

Wait for a date when all required attendees can be available onsite.


C.

Run separate meetings to accommodate everyone's schedule.


D.

Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.


Expert Solution
Questions # 502:

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?

Options:

A.

Consider cultural differences among stakeholders.


B.

Conduct an integration meeting among all stakeholders.


C.

Schedule communication training for management-level stakeholders.


D.

Understand how political aspects can affect the project.


Expert Solution
Questions # 503:

A company is initiating a project to decommission inefficient sales channels. Several stakeholders argue that one channel that indicates a downturn in generating value is still more efficient than some of the channels that are planned to remain.

What should the project manager do?

Options:

A.

Plan for incremental and iterative delivery based on feedback from the marketing and sales team.


B.

Review and update the success criteria to ensure that the channel is not decommissioned.


C.

Inform the stakeholders that the list of channels to be decommissioned was approved by the CEO.


D.

Escalate the objection to the steering committee and human resources (HR) as a personal intimidation incident.


Expert Solution
Questions # 504:

A project needs to purchase a specific piece of equipment, as stated in the

project documents and approved by the project sponsor. The procurement division is

questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.

What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?

Options:

A.

Communicated the project charter to the procurement division


B.

Included a procurement division member on the project team


C.

Reminded the project sponsor about the procurement division's reputation


D.

Communicated the project management plan to the procurement division


Expert Solution
Questions # 505:

A project manager is working on a large project with a very difficult client. During

the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?

Options:

A.

Concentrate on the current project milestones.


B.

Update the project management plan for this new work.


C.

Develop a business case and submit it to the client.


D.

Make all the changes and then show the client the results.


Expert Solution
Questions # 506:

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

Options:

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.


B.

Review the operations manager's concerns and ensure these concerns are addressed


C.

Escalate the concerns to the project sponsor and discuss options to address them


D.

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.


Expert Solution
Questions # 507:

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

Options:

A.

Meet with the team to reinforce their responsibilities and the consequences if theproject deliverables are not completed on time.


B.

Apply additional controls to the project deliverables to ensure that all milestonesare achieved on time.


C.

Contact the functional manager to ensure that team motivation remains high untilthe end of the project.


D.

Schedule a team event with the project sponsor to highlight the importance of theproject and recognize the work of the team.


Expert Solution
Questions # 508:

A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

Options:

A.

Focus on remediation not merely on correcting symptoms


B.

Compare the team's performance against other project teams


C.

Identify potential failure points based on the iteration workload


D.

Motivate the team to perform better


Expert Solution
Questions # 509:

In an agile project, the project manager notices that one team member rarely reports blockers during daily check-ins. Additionally, the team member is too shy to participate in team activities and prefers to provide status updates individually to the project manager.

How should the project manager rectify this situation?

Options:

A.

Review team culture and the personality traits of the individual to address status update gaps.


B.

Create a safe space for status updates and encourage the team to approach the project manager.


C.

Review the team status updates more thoroughly to address the gaps.


D.

Support team inclusion and change the format of status updates to email.


Expert Solution
Questions # 510:

A project manager is leading a council's project that aims to ensure full compliance with health, ecological, and environmental standards.

At the same time, the project's goal is to remain fully adherent to the council's values, policies, and procedures.

How should the project manager ensure project success?

Options:

A.

Enforce the project manager's authority over the contracting partner delivering to the council. by


B.

Engage a third-party consulting firm to oversee the project's implementation.


C.

Develop the necessary implementation plan and ask the partners to adjust their plans to meet the project manager's objectives.


D.

Meet with the stakeholders regularly to share project objectives and mutually agree on common goals and plans.


Expert Solution
Questions # 511:

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?

Options:

A.

Review the project scope statement


B.

Confirm ownership for ongoing value realization


C.

Escalate the issue to the project sponsor


D.

Appraise the stakeholders of value gain progress


Expert Solution
Questions # 512:

During a meeting for product review, a key stakeholder announces that because they are receiving adequate information about the project they will not attend any further meetings. What should the project manager do?

Options:

A.

Log this as an issue in the issue log and address it with the project sponsor.


B.

Ignore the stakeholder as the product is almost complete.


C.

Explain that the needs will be updated in the stakeholder engagement plan.


D.

Inform the stakeholder that changes can happen in this project.


Expert Solution
Questions # 513:

A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.

How should the project manager proceed in order to complete the risk register?

Options:

A.

Cancel the meeting and create the risk register using the project documents.


B.

Continue the meeting and send the updated risk register to all stakeholders.


C.

Run the meeting and follow up with each one of the absent stakeholders to get their input.


D.

Escalate the issue of stakeholders not attending the meeting to the project sponsor.


Expert Solution
Questions # 514:

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?

Options:

A.

Keep the project focused and executed in silos for better outcomes.


B.

Report the concern to the agile project management office (PMO),


C.

Inform the product owner of the concern so that i can be addressed.


D.

Open up to the team to work collaboratively to achieve the outcomes.


Expert Solution
Questions # 515:

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?

Options:

A.

Discuss the vacation plan and include scheduling changes in the change log database.


B.

Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.


C.

Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.


D.

Push out the project timeline according to the vacation plan in place based on the recent company policy.


Expert Solution
Questions # 516:

A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,

yet some stakeholders lack an understanding of how it will provide value to the organization.

What should the project manager do next?

Options:

A.

Ask the sponsor to identify requirements for a new project to monitor and report achievement of the benefits.


B.

Direct the team to implement the benefits management plan and track achievements before the end of the project.


C.

Coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.


D.

Update the work breakdown structure (WBS) and project schedule with tasks and resources to track benefits realization.


Expert Solution
Questions # 517:

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?

Options:

A.

Establish the project scope and set clear team objectives


B.

Set performance standards and direction


C.

Hold early kick-off meetings and regular weekly meetings


D.

Select members for their skill or potential


Expert Solution
Questions # 518:

A protect team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed The main issue is that the team member does not understand a new system that was recently implemented

What should the project manager do?

Options:

A.

Ask the team member to learn the new system as on-the-job training


B.

Issue a change request to extend the project schedule


C.

Escalate the team members performance to the project sponsor


D.

Assign an experienced resource to support the team member


Expert Solution
Questions # 519:

The project management office (PMO) has recently adopted some agile practices. During an iteration a key stakeholder in the business is concerned with the benefits management plan in the project document repository and mentions that some benefits have not been updated.

What should the project manager do first?

Options:

A.

Update the risk register in order to add the issue.


B.

Review the issue log regarding the concern


C.

Revise the benefits management plan


D.

Assess the repository to check for inconsistencies.


Expert Solution
Questions # 520:

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.

Request for information


B.

Scope statement


C.

Issue log


D.

Risk register


Expert Solution
Questions # 521:

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

Options:

A.

Resource management and lessons learned


B.

Time management and stakeholder engagement


C.

Cost management and risk management


D.

Stakeholder engagement and lessons learned


Expert Solution
Questions # 522:

A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team

What should the project manager do?

Options:

A.

Send a formal communication regarding the missed milestone


B.

Delay sending a formal communication until the project team catches up


C.

Ask for a meeting with the sponsor to decide whether to send the formal communication


D.

Forego the formal communication and have a conversation with the supervisor


Expert Solution
Questions # 523:

One of the project manager's important assignments is to formally revise project compliance as it pertains to user data protection regulations. What should the project manager

do to monitor compliance?

Options:

A.

Assess the risk register.


B.

Conduct project reviews.


C.

Perform retrospectives.


D.

Complete sprint reviews


Expert Solution
Questions # 524:

A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,

What should the project manager do first?

Options:

A.

Review the stakeholder engagement plan.


B.

Review the communications management plan.


C.

Send the CEO one executive summary per week instead of five reports per week.


D.

Meet with the team and decide the type and frequency of the reports to send to the CEO.


Expert Solution
Questions # 525:

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

Options:

A.

Move the solution designer to another team.


B.

Review the process that resulted in this situation.


C.

Stop work until the design document is completed.


D.

Ask the team to document the design.


Expert Solution
Questions # 526:

A company has a transformation project in progress. During a planning session, several stakeholders are in constant disagreement and often use personal arguments to support their position. Team members are getting frustrated with the situation.

What should the project manager have done to avoid this situation?

Options:

A.

Established ground rules before the discussion had started.


B.

Asked stakeholders not to voice their opinions during the meeting.


C.

Invited a high-level sponsor to the meeting to reduce the level of disagreement.


D.

Reinforced that higher-level management has the decision power.


Expert Solution
Questions # 527:

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

Options:

A.

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget


B.

Engaged with the project sponsor to ensure support for the project manager's decision


C.

Conducted a meeting with the functional manager to explain why the activities needed to be stopped


D.

Convinced the functional manager to stop the activities that will run beyond the budget


Expert Solution
Questions # 528:

A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?

Options:

A.

Consult preferred vendors from the company.


B.

Perform research on experienced vendors in the market.


C.

Source vendors with extensive experience.


D.

Follow the company's standard vendor selection criteria process,


Expert Solution
Questions # 529:

An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?

Options:

A.

Ask the product owner to stop accommodating further changes to the scope


B.

Leverage the product owner to monitor the external environment


C.

Accommodate the critical and urgent changes in the current iteration


D.

Suggest to the product owner to execute the changes in a separate project


Expert Solution
Questions # 530:

we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.

What should the project manager do?

Options:

A.

Discuss the issue with the team to resolve the disagreement.


B.

Ensure that there is consensus among the project stakeholders.


C.

Discuss the issue during the next sprint planning meeting.


D.

Support the outcome of the architects’ agreement.


Expert Solution
Questions # 531:

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?

Options:

A.

Review organizational process assets (OPAs) for clarity.


B.

Document lessons learned before closing.


C.

Consult the project charter for next steps.


D.

Confirm the definition of done (DoD) has been met.


Expert Solution
Questions # 532:

During a status review meeting a team member raises concerns about tasks that are not being completed due to an underperforming resource on the team. What should the project manager do first?

Options:

A.

Ask the team to solve the issue internally and review the underperforming resource's situation


B.

Meet with the team member privately to discuss the problem and work together to find a solution


C.

Contact the functional manager and request to replace the team member with a better resource


D.

Discuss various options to improve the team member's performance with their functional managers


Expert Solution
Questions # 533:

Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.

What should the project manager do to address this concern?

Options:

A.

Schedule a dedicated session to review the team charter.


B.

Set up a meeting with the team member to review the team charter.


C.

Ask another team member to meet with this team member for a discussion.


D.

Send a reminder to the team member about the rule being violated.


Expert Solution
Questions # 534:

A project manager was recently assigned to a new project that is about to start. The

organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

Options:

A.

Create an issue log template that will be used to identify and track impediments.


B.

Create a contingency plan in case the project deviates from the initial plan.


C.

Create a schedule management plan to ensure the project meets the delivery date.


D.

Create an assumption log and map assumptions to impediments based on the impact tothe project value.


Expert Solution
Questions # 535:

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

Options:

A.

Allow team members to resolve personal issues without involving the project manager


B.

Arrange and conduct team-building sessions to improve team effectiveness


C.

Obtain feedback from the isolated team member to understand the situation


D.

Get feedback from other team members to understand what led to this situation


E.

Identify the isolated team member as a risk and document the situation in the risk register.


Expert Solution
Questions # 536:

An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?

Options:

A.

Laissez-faire


B.

Transactional


C.

Transformational


D.

Charismatic


Expert Solution
Questions # 537:

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

Options:

A.

Work with the team to understand and solve the issues


B.

Provide testing training to all the project team members


C.

Increase the sprint duration so the testing can be completed


D.

Add a new resource with testing skills to the team


Expert Solution
Questions # 538:

A large and complex program in an agile environment has experienced an increase in

escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process.

What should be done to resolve this issue?

Options:

A.

Invite the client and product owner to all planning, review, and retrospective meetings.


B.

Accept the escalations and manage them so the working relationship with the client isnot impacted.


C.

Review and clarify roles, responsibilities, and the governance model at the next sprintreview meeting.


D.

Invite the product owner to attend all Scrum meetings and define the governance modeland escalation path.


Expert Solution
Questions # 539:

A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.

What should the project manager do?

Options:

A.

Remind the team that their primary responsibility is software development.


B.

Add a user story to the product backlog to test the software product.


C.

Discuss the Option in the next daily standup meeting to finalize the decision.


D.

Recommend the option to the product owner for consideration.


Expert Solution
Questions # 540:

A project manager working on a software development project asked the software development about the status of a task. The developer responded that the task was delivered 1 week ago and mentioned that the delivery was reported via a specific project management software.

What should the project manager do next?

Options:

A.

Review the stakeholder engagement plan and communicate which technology is available to develop, transmit, and store project artifacts.


B.

Engage the software developer, let them work with this project management software, and then conduct a train-the-trainer activity to ensure everyone can use it.


C.

Research the project management software to understand how it works, and establish it as the acceptable software to hold the project artifacts.


D.

Review the communications management plan and communicate which technology is to be used to develop, transmit, and store project artifacts,


Expert Solution
Questions # 541:

A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery

How should the project manager avoid this situation in the future?

Options:

A.

Use the same methods until the end of the current delivery and suggest new ones during the retrospective.


B.

Refer to the policies and frameworks used at the company enterprise level and inform the project team members.


C.

Tell the sponsor that the project manager will use their own communication model to ensure on-time delivery.


D.

Agree with the project team on a suitable collaboration and make sure information is shared at all times


Expert Solution
Questions # 542:

A project manager needs the team to define the steps and identify the risks of migrating data to a new system.

What type of leadership should the project manager use to accomplish this?

Options:

A.

Laissez-faire


B.

Transformational


C.

Dynamic


D.

Servant


Expert Solution
Questions # 543:

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

Options:

A.

Organize a brainstorming session with the project team to address the issue.


B.

Advise the project team on the importance of team engagement,


C.

Invest in coaching and training for all project team members.


D.

Escalate the issue with the human resource (HR) department to take action,


Expert Solution
Questions # 544:

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do'?

Options:

A.

Escalate the issue to the sponsor and ask for stakeholder engagement


B.

Review the project business case and update it periodically


C.

Plan for strategic program management


D.

Implement a communications management plan


Expert Solution
Questions # 545:

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important

milestone in a week.

What should the project manager do next?

Options:

A.

Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.


B.

Perform market research to find out if there are other vendors that can produce similar kinds of materials.


C.

Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.


D.

Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.


Expert Solution
Questions # 546:

Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.

What should the project manager do to engage the stakeholders?

Options:

A.

Ask the team to work on the complaint raised by the clients.


B.

Escalate the issue raised by the clients to the project sponsor,


C.

Develop a solution with the team to identify the inventory level.


D.

Work with the team and the product owner to define the next steps.


Expert Solution
Questions # 547:

Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution

document.

What should the project manager do to avoid a delay in the project?

Options:

A.

Ask the accounting manager to delegate a team member who can support the project.


B.

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,


C.

Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,


D.

Begin discussions with other functional managers and meet with the accounting manager later.


Expert Solution
Questions # 548:

A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.

What should the project manager do?

Options:

A.

Meet with the project sponsor to explain that the project cannot be completed as planned


B.

Meet with the technical lead to review the sprint plan


C.

Meet with the product owner to confirm the minimum viable product (MVP) option


D.

Meet with the project team and reprioritize the backlog


Expert Solution
Questions # 549:

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

Options:

A.

Fast tracking


B.

Resource leveling


C.

Critical chain method


D.

Schedule crashing


Expert Solution
Questions # 550:

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

Options:

A.

Work with the product owner to evaluate and prioritize the requirements


B.

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list


C.

Determine the expected benefits of each requirement to maximize the overall business value


D.

Prioritize the requirements based on the hierarchical level of the requesting stakeholders


Expert Solution