Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 10 out of 13 pages
Viewing questions 451-500 out of questions
Questions # 451:

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

Options:

A.

Escalate the issue to the project sponsor.


B.

Review the stakeholder engagement plan.


C.

Update the issue log.


D.

Neutralize the negative stakeholders.


Expert Solution
Questions # 452:

A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management.

What should the project manager do first?

Options:

A.

Review the benefits of the proposed changes in relation to the business case.


B.

Assess the time overrun, and start implementation to avoid additional delays.


C.

Request a provisional budget increase to avoid any budget overruns.


D.

Motivate the team to avoid the frustration of working on a prolonged project.


Expert Solution
Questions # 453:

An agile project is starting its seventh out of eight iterations In a planning meeting, the team realizes that an unidentified risk became an issue and the contingency reserve has to be used.

What should the project manager do?

Options:

A.

Ask the sponsor to approve inclusion of an additional iteration to the project


B.

Ask the team to include the contingency plan in the iteration backlog


C.

Help the team review the project approach to initiate the corrective actions


D.

Ask the sponsor for money to implement the contingency plan.


Expert Solution
Questions # 454:

In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain

What should the project manager do?

Options:

A.

Make sure the analyst has regular pairing meetings with the other team member throughout task execution


B.

Ask the analyst to use skills to develop the tool, then move development to another team member


C.

Enroll the analyst in a capacity-building program and keep this analyst assigned to the task


D.

Recognize the analyst's concerns and reassign the task to another team member


Expert Solution
Questions # 455:

According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.

What should the project manager do?

Options:

A.

Record it in the risk register


B.

Ask the client to help solve the problem


C.

Start procuring this material from another supplier.


D.

Engage the project team to look for alternatives to find a solution


Expert Solution
Questions # 456:

A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.

What should the project manager have done to avoid this situation?

Options:

A.

Established daily standup meetings to track and report on team progress and escalated delays to stakeholders as they occurred


B.

Set up weekly status meetings to review team progress, prepared weekly status reports to track progress and regularly escalated delays


C.

Met with the team, allowed team members to make decisions about what to do and established performance goals


D.

Conducted routine meetings and identified team members who are under performing


Expert Solution
Questions # 457:

A stakeholder is requesting that the project manager share project status updates

on a regular basis. This stakeholder is not included in the regular distribution list.

What should the project manager do?

Options:

A.

Start sending status updates to this stakeholder based on the request.


B.

Ask the stakeholder's manager if the stakeholder can be added to the list.


C.

Review the stakeholder engagement and communications management plans.


D.

Escalate the stakeholder’s request to the project sponsor.


Expert Solution
Questions # 458:

The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?

Options:

A.

Reschedule the project execution date.


B.

Continue project execution using the current blueprints from the client.


C.

Escalate this issue to the project sponsor


D.

Consult with the client to determine if project execution should be continued.


Expert Solution
Questions # 459:

A year after implementing a policy change to improve diversity and inclusion within two teams, there is increasing conflict within the company What should have been done to prevent this conflict?

Options:

A.

The organization should have introduced the concept of diversity broadly


B.

The leadership team should have worked closely with the marketing team to get insight on diversity


C.

Organization-wide diversity training should have been provided to the workforce


D.

The critical departments in the organization should have been involved in this exercise


Expert Solution
Questions # 460:

A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.

What should the project manager do?

Options:

A.

Seek help from the project sponsor to get an SME from another team in the organization.


B.

Provide an opportunity to one of the existing team members to become an SME.


C.

Hire a contractor from outside of the organization to continue with the project.


D.

Ask team members to document the issue and address it in the next project meeting.


Expert Solution
Questions # 461:

A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.

What should the project manager do first?

Options:

A.

Organize a conference call with the internal expert and the client to estimate the amount of effort required to fix it.


B.

Decline the request politely since the issue, although critical, is not the responsibility of the project team.


C.

Allocate a task to the team member as a high priority and inform the customer that the issue will be resolved the next day.


D.

Inform the customer that they should contact the sales manager and submit a formal request for a quote.


Expert Solution
Questions # 462:

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

Options:

A.

Adjust the original budget estimates with the current cost variance.


B.

Negotiate the project changes and adjust stakeholder expectations.


C.

Perform a root cause analysis of the project performance.


D.

Review the activity duration to reforecast the project completion date.


Expert Solution
Questions # 463:

A company has agreed to run a transformation project using agile approaches.

During the implementation, there is pushback from the functional groups that the project is moving too fast.

What should the project manager have done at the beginning of the project to prevent this from happening?

Options:

A.

Circulated the project charter


B.

Assessed the organizational culture


C.

Determined the level of maturity of the employees


D.

Communicated the project schedule


Expert Solution
Questions # 464:

A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team

requests a change in the sprint goals and sprint backlog items.

What should the project manager do?

Options:

A.

Create a parallel sprint to deliver the additional items.


B.

Guide the agile team to add the new scope to the product backlog.


C.

Pause the sprint to allow time to include the new items.


D.

Moderate the expectations for sprint quality.


Expert Solution
Questions # 465:

A subcontracting company is presenting its feature release A key stakeholder is asking to add a new feature to the product How should the project manager deal with the new requirement?

Options:

A.

Follow the change management process and work with procurement if needed


B.

Engage an arbitrator to resolve any conflict while handling the new requirement


C.

Add the change to the next sprint to meet the customer's needs


D.

Allocate resources to work on the new feature immediately to complete the request


Expert Solution
Questions # 466:

A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards

What should the project manager do?

Options:

A.

Set up a structured, independent processes to determine if project activities followed the standards.


B.

Schedule training for the project team on the new regulations introduced by the government agency


C.

Evaluate the impact the new regulations will have on the project and submit a change request


D.

Update the lessons learned register and inform senior management of the new standards


Expert Solution
Questions # 467:

A project sponsor receives project information and updates in a timely manner, but

the sponsor is concerned because key information is missing in the reports. What should the

project manager do?

Options:

A.

Review the communication needs of key stakeholders.


B.

Confirm that the project information is understood and feedback is received.


C.

Determine communication methods, frequency, and level of detail.


D.

Provide all project information to the stakeholder.


Expert Solution
Questions # 468:

An organization in a regulated industry has decided to switch from a predictive to

an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum,

and the project manager is still accountable for the project outcomes. During the fourth sprint

demo, the customer notices that a feature is not compliant with the regulations.

What should the project manager do?

Options:

A.

Have the team consult with the compliance officer to update the definition of done(DoD) for the user stories in the past sprint.


B.

Have the product owner consult with the change control board (CCB) to have thenecessary compliance requirements implemented.


C.

Have the scrum master organize a weekly meeting with the compliance officer, theproduct owner, and the project team.


D.

Have the product owner review the user stories in the product backlog with thecompliance officer on a regular basis to identify any gaps.


Expert Solution
Questions # 469:

A project manager has just been assigned to a project to build new software for a client. All the requirements have been gathered.

What should the project manager tell the team members to focus on?

Options:

A.

Reducing cost for the customer


B.

Delivering value to the customer


C.

Working together as a team


D.

Finishing the project on schedule


Expert Solution
Questions # 470:

Match the project situation on the left to the meeting on the right where the situation could occur.

Question # 470


Expert Solution
Questions # 471:

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

Question # 471


Expert Solution
Questions # 472:

A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?

Options:

A.

Document the lessons learned and implement improvements in the next sprint


B.

Facilitate a daily standup with the team to track the implementation of changes


C.

Organize a demonstration of the changes in the enterprise system


D.

Request that all team members think of ideas to improve processes.


Expert Solution
Questions # 473:

A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.

What immediate action should the project manager take to improve the situation?

Options:

A.

Communicate this issue to the human resources department.


B.

Provide additional training to the new hire.


C.

Increase team cohesiveness by sharing information and experiences openly.


D.

Update the issue log and define the mitigation strategy.


Expert Solution
Questions # 474:

After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?

Options:

A.

Comply with the project sponsor's request to not archive the project artifacts.


B.

Document the project sponsor's instructions as the archived project artifacts.


C.

Archive the project artifacts on the project manager's local computer for future reference


D.

Consult with the project management office (PMO) for guidance on project artifacts.


Expert Solution
Questions # 475:

A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?

Options:

A.

Assign the feature to another team member, and have them try to complete the feature by the end of this iteration


B.

Review team capacity and reassign the functionality to additional iterations as required


C.

Determine if the team member can work from home to complete the functionality.


D.

Review the work in progress with the product owner to determine the next step


Expert Solution
Questions # 476:

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant

business value. What should the project manager do?

Options:

A.

Call the stakeholder to tell them that the final product schedule must be extended due to this last minute, urgent request.


B.

Perform an impact analysis and share the overall schedule impact before deciding on a new priority.


C.

Reject the new requirement from the sponsor as this is going to impact the delivery of the stakeholder's final product.


D.

Ask the product owner to prioritize the new request from the sponsor and ask the team to work on it immediately.


Expert Solution
Questions # 477:

A project manager Is transitioning from a predictive We cycle project to a new agile project How should the project manager manage and control the scope for the new project?

Options:

A.

Create a scope baseline and put the rest as backlog activities.


B.

Estimate the work the team can complete and define story sizes to keep the project under control.


C.

Develop a plan to complete more work In less time.


D.

Spend a short amount of time defining the scope and building prototypes to refine the requirements.


Expert Solution
Questions # 478:

A project team is conducting a retrospective. The team wants to identify what had

a positive impact on the velocity and keep doing it.

Click on the area that the team should focus on to identify good practices.

Question # 478


Expert Solution
Questions # 479:

A company has made multiple staff and operational changes over the last several years, significantly improving the company culture. A project manager was recently assigned to report to a new project supervisor. The project manager notices the supervisor's style of leadership is about getting the job done in the shortest possible time regardless of operational and worker impacts. This is causing some complaints from workers.

How should the project manager handle this situation?

Options:

A.

Discuss the company culture with the supervisor to clarify expectations.


B.

Review the overall organizational culture of the company again.


C.

Request that the new supervisor be assigned to another project.


D.

Explain to the workers that they need to listen to the supervisor.


Expert Solution
Questions # 480:

A specialized team member has just received news that they must leave the office for several weeks They have approximately two workdays until they will leave and then they will become unavailable through any communication channels. There is a key deadline approaching

What should the agile project manager do?

Options:

A.

Ask the team member to complete as much as they can now.


B.

Ask the team member to work with their peers to knowledge share


C.

Ask the team member to identify their specialist tasks


D.

Ask the team member to host a special team meeting.


Expert Solution
Questions # 481:

A project manager is hired by a global company. The project manager is an agile specialist and is tasked with supporting the project team to reduce rework and dissatisfaction.

How should the project manager address these objectives?

Options:

A.

Decrease the scope of the portfolio and send new solutions to the customer.


B.

Deliver a schedule with the portfolio timeline and delivery to the customer.


C.

Adopt an incremental cycle of delivering value to the customer.


D.

Prepare deliveries with more details to satisfy the customer.


Expert Solution
Questions # 482:

An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance

team is requesting a project budget for the new product.

What should the team do to address this request?

Options:

A.

Work with the finance team to transition to incremental budgeting.


B.

Request the finance team to allocate a budget based on historical data.


C.

Provide the budget to the finance team for only the planned increments.


D.

Extrapolate the budget based on the current cost performance index (CPI).


Expert Solution
Questions # 483:

At the end of a project, the project manager is asked to submit project documentation for an internal audit in response to regulatory requirements. What should the project manager have done at the beginning of the project to ensure that project documentation would

fulfill these requirements?

Options:

A.

Conducted a document review


B.

Confirmed documentation requirements with stakeholders


C.

Updated the project templates


D.

Implemented a new change control policy


Expert Solution
Questions # 484:

A project manager is leading a product development project that requires high involvement from several stakeholders. What should the project manager do to ensure this involvement?

Options:

A.

Evaluate the engagement needs of stakeholders.


B.

Distribute weekly status emails to stakeholders.


C.

Engage the sponsor on the behavior of stakeholders.


D.

Conduct weekly update meetings with stakeholders.


Expert Solution
Questions # 485:

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

Options:

A.

Prepare a risk report that captures the probability and impact of risks, and then shareit with the project sponsor.


B.

Share the organization's decision with the team and make plans to adopt an agileapproach in the upcoming project.


C.

Make a request to human resources for new team members who have agileexperience.


D.

Ask the project sponsor to change the approach back to predictive as that is theteam’s strength.


Expert Solution
Questions # 486:

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.

What should the project manager do next?

Options:

A.

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.


B.

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.


C.

Address this concern with the functional managers to ensure there will be no further delays.


D.

Schedule a meeting with all of the functional managers to resolve the resource conflicts.


Expert Solution
Questions # 487:

A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.

How should the project manager communicate the organizational culture and project goal to these stakeholders?

Options:

A.

Hire a company to advertise the project and company through a media outlet.


B.

Prepare a report outlining the organizational structure and project parameters.


C.

Take the stakeholders out informally and verbally brief them about the organization and project.


D.

Ask a team member to directly address the information needs of the stakeholders.


Expert Solution
Questions # 488:

In the middle of an iteration a team member suggests a new method of doing things The method provides no value to the end customer, however it may help the team to work more efficiently The change may require several days of work to implement

How should the project manager respond to the suggestion?

Options:

A.

The change should be considered and immediately added to the product backlog.


B.

The change should be considered and presented to the project sponsor for approval


C.

The change should be considered because it will help the team work more efficiently


D.

The change should not be considered because it adds no value to the end customer


Expert Solution
Questions # 489:

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

Options:

A.

Look for processes that cause bottlenecks and slow down the team's agility


B.

Assign the items with high complexity lo senior developers


C.

Empower the learn to make decisions to remove impediments


D.

Work with the team to remove impediments as quickly as possible


E.

Move the items with high complexity to the last iterations


Expert Solution
Questions # 490:

A team has been working together for several months and has successfully

delivered work. A new team member has joined the team but is having difficulty

contributing.

What should the project manager do to help the new team member integrate effectively?

Options:

A.

Give the new team member time to contribute until they ask for help and support.


B.

Assign the new team member tasks so that the team member knows on what to focus.


C.

Approach the team member to identify any issues and then plan a resolution accordingly.


D.

Review the project with the team member to ensure the project scope is understood


Expert Solution
Questions # 491:

A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?

Options:

A.

Propose a solution redesign for the project


B.

Perform risk analysis against the issue.


C.

Revise the project's quality control measurements


D.

Develop a mitigation based on the solution design


Expert Solution
Questions # 492:

A project manager has joined a company m an unfamiliar industry and has been given a strategically important project Being new, and not fully understanding the interdependences of the various departmental work items, the project manager is unsure of how to plan the project

How should the project manager proceed?

Options:

A.

Consult the project sponsor and request their feedback


B.

Consult the product owner and request a complete prioritization session


C.

Consult a senior project manager within the organization and request their expert judgement


D.

Consult a senior developer within the organization and request their input.


Expert Solution
Questions # 493:

A project management team received news that a competitor has released the

latest version of a program. What should the team do next?

Options:

A.

Review the project plan to evaluate if any updates should be made.


B.

Crash the existing schedule with additional resources to deliver more features.


C.

Stop the project immediately as the market opportunity has already been missed.


D.

Continue with the project plan and target delivery date as expected.


Expert Solution
Questions # 494:

A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?

Options:

A.

Request the team member to move to another team.


B.

Delegate other team members to complete this team member's tasks.


C.

Mentor the team member and provide the necessary training.


D.

Include this team member in an improvement program through a human resources request.


Expert Solution
Questions # 495:

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?

Options:

A.

Ensure that customer requirements do not change from the start of the project.


B.

Ensure that the definition of done (DoD) is well defined and complete for future iterations.


C.

Ensure that the development and quality assurance team members implement the feature correctly.


D.

Ensure that the team facilitator allocates tasks correctly to team members.


Expert Solution
Questions # 496:

A senior management team member contacts an agile project lead and mentions

that certain features the senior manager thought would be in the current release were not

included. What should the agile project lead do?

Options:

A.

Assure the senior manager that these features will be queued up in the next sprint.


B.

Meet with the team to understand why the senior manager’s features were not included.


C.

Invite the senior manager to the next planning meeting.


D.

Send the product roadmap to the senior manager.


Expert Solution
Questions # 497:

A project is being initiated, and almost every resource available on the project team is a recent university graduate. What should the project manager do to ensure their engagement with the project?

Options:

A.

Provide clear direction on the work to be done and its alignment to the major objectives of the organization, using technology to communicate.


B.

Establish a clear hierarchical environment and allow them to navigate through the project faster using social networks.


C.

Foster proactive decision making and develop a hierarchy to approve decisions based on different levels of complexity.


D.

Create an environment that encourages leadership, translates ambitions into growth opportunities, and rewards overtime workers.


Expert Solution
Questions # 498:

A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.

What should the newly assigned project manager do first to understand the issues?

Options:

A.

Escalate the issues to the project sponsor.


B.

Review the issues log to ensure the issues are captured.


C.

Check the risk management plan to ensure there is a strategy to address the issues.


D.

Ask the key stakeholders to discuss the issues with the project team.


Expert Solution
Questions # 499:

A large organization decided to adopt an agile methodology based on the trends

seen in the industry. The organization invested a large amount of money in adopting it, but

after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

Options:

A.

Conducted agile training for all employees ranging from the project teams throughmid-level to upper-level management.


B.

Conducted a postmortem and captured the learning in organizational process assets(OPAs) for future use.


C.

Assessed the organization's culture, performed a suitability analysis, and determinedthe future state.


D.

Hired a third-party agile delivery team to do the implementation.


Expert Solution
Questions # 500:

For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product

After collecting the new requirements, what should the project manager do?

Options:

A.

Assess the impact of the new requirements and initiate the change request process.


B.

Work with the product manager and the rest of the team to update the project backlog.


C.

Assess the impact and communicate the updated product roadmap to the stakeholders.


D.

Follow the change management plan to update the risk register so It accounts for the added scope.


Expert Solution
Viewing page 10 out of 13 pages
Viewing questions 451-500 out of questions