Questions # 451:

A customer interacts directly with a Scrum team and continually requests changes in

priorities. This causes confusion among the team members and they complain to the project

manager.

What should the project manager do?

Options:

A.

Advise the customer to discuss changes with the product owner.


B.

Document this issue in the sprint backlog for discussion at a team meeting.


C.

Ask the customer to submit a change request to the project sponsor.


D.

Encourage the team to clarify the requests with the customer.


Expert Solution
Questions # 452:

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?

Options:

A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics


B.

Stop the project and kick off another project to apply alternative wires for the machine


C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider


D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine


Expert Solution
Questions # 453:

A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager's approval.

What should the project manager do?

Options:

A.

Update the issue log and review the lessons learned register for options


B.

Implement conflict resolution to accommodate the team's needs


C.

Implement decision-making techniques to advance the stones


D.

Empower the team to self-organize and make their own decisions


Expert Solution
Questions # 454:

A team is developing an experimental program to be used by the public. What should

the project manager do to ensure the desired benefits are achieved?

Options:

A.

Ensure that the project team fully tests the program.


B.

Ensure a review is done with a representative group of users.


C.

Meet with government officials to review policy requirements.


D.

Document the features fully and update the specifications.


Expert Solution
Questions # 455:

A project team delivered a critical deliverable to the customer. The customer

complained that the maintenance manual was not included.

What should the project manager do next?

Options:

A.

Submit a change request to include the manual.


B.

Add the needed manual and update the risk log.


C.

Review the stakeholder engagement plan.


D.

Review the terms and conditions of the contract.


Expert Solution
Questions # 456:

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

Options:

A.

Request a reserve analysis and update the risk management plan


B.

Update the risk response plan to include the needed reserve


C.

Perform a schedule network analysis to avoid any critical path delays


D.

Review the risk response plan to verify inclusion of the needed reserve


Expert Solution
Questions # 457:

A project manager is leading an integration project for a retail company. The project

demands a lot of time from the stakeholders to make important business decisions. The

project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this

project?

Options:

A.

Schedule meetings with all of the stakeholders to make business decisions when

needed.


B.

Share the project schedule, milestones, and meeting agendas with the stakeholders

ahead of time.


C.

Work with the available stakeholders to make business decisions and keep all

unavailable stakeholders informed.


D.

Add time reserve in the project schedule to allow extra time for the stakeholders to

make decisions.


Expert Solution
Questions # 458:

A project manager is assigned to lead a design for a new version of an existing

product with the technology and operations teams. The project manager organizes a joint

requirements session to determine the most practical ideas. The project manager was advised

that the session may become chaotic.

What should the project manager do to ensure the session is interactive, productive, and

efficient?

Options:

A.

Pick the senior and experienced staff members from both teams and arrange face-toface interviews.


B.

Organize a formal session led by a skilled facilitator with defined rules for how

participants will interact with one another.


C.

Distribute a questionnaire on the key features of the product and encourage the teams

to respond with their design recommendations.


D.

Hold multiple sessions of manageable sizes with participants from both teams to

discuss their ideas.


Expert Solution
Questions # 459:

A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project

How should the project manager report this cost?

Options:

A.

Estimate user story points and forecast a budget for that deliverable


B.

Determine the control accounts and use a top bottom estimate


C.

Consider the cost performance index (CPl) based on earned value (EV) divided by costs


D.

Calculate the budget at completion (BAC) based on the completed and planned features


Expert Solution
Questions # 460:

During the sprint planning of a project, the team members have a disagreement

about the comparative size of the backlog items and if they would fit into the next sprint.

Considering a hybrid approach, what should the project manager do?

Options:

A.

Ask an external technical leader to provide input and plan the sprint.


B.

Remove the items from the product backlog since the size couldn't be estimated.


C.

Make the decision about the backlog items based on what makes more sense.


D.

Facilitate the discussion so that the team members can reach a consensus.


Expert Solution
Questions # 461:

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

Options:

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep


B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place


C.

Advise the team not to engage in modifications unless it follows the proper change approval process


D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced


Expert Solution
Questions # 462:

A project team consists of members based in country A and subject matter experts

(SMEs) based in country B with a 12-hour time difference. What can the project manager do

to improve interactions between the team members in both countries?

Options:

A.

Ensure full participation of both the product owner and business SMEs in scope

planning sessions.


B.

Identify virtual communication methods and arrange for regular team meetings

accordingly.


C.

Explore the opportunity to have both teams colocated.


D.

Plan for frequent face-to-face meetings.


Expert Solution
Questions # 463:

An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time

What should the project manager have done to avoid this delay?

Options:

A.

Updated the stakeholder engagement plan to reflect a change in the product owner


B.

Communicated the status of the project more frequently with the product owner


C.

Updated the communications management plan to reflect a change in the communication needs


D.

Reevaluated the new product owner's needs for better engagement


Expert Solution
Questions # 464:

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

Options:

A.

Include additional mitigation actions against feature defects and update the risk management plan.


B.

Assess the relevance of the feature and then analyze the submission of a change request to descope it.


C.

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.


D.

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.


Expert Solution
Questions # 465:

A project manager is working on a cost-reimbursable contract from the client's side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract

What should the project manager do?

Options:

A.

Request a change in the contract in order to add the deliverable


B.

Add this deliverable to the requirements traceability matrix


C.

Terminate the contract and commence the closeout process


D.

Look to see if the deliverable is described in the statement of work (SOW)


Expert Solution
Questions # 466:

A project manager is working with an agile team to enhance a product. Due to a

tight deadline, the team is trying to crash the schedule by engaging multiple resources to work

on the project simultaneously. However, the technical environment is configured to allow only

one resource to work on a feature at a time. The team plans to upgrade the technical

environment but is unable to agree on a way forward.

What should the project manager do first?

Options:

A.

Conduct a consensus-building session to decide how to approach the next set of work.


B.

Escalate the issue to the product owner for resolution.


C.

Add this conflict to the agenda for discussion at the next daily standup meeting.


D.

Conduct a planning session to decide how to approach the next set of work.


Expert Solution
Questions # 467:

One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.

What should the project manager do next?

Options:

A.

Arrange an additional meeting with the team to communicate the agreement made during the last meeting.


B.

Schedule a new meeting to evaluate the agreement and negotiate a new one.


C.

Talk with the team member and explain that once the meeting ended, the agreement must be respected.


D.

Meet with the team member and search for the root cause of their behavior.


Expert Solution
Questions # 468:

A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?

Options:

A.

Advise the team to adjust their work habits and behaviors to allow for better conflict resolution


B.

Call a team meeting to discuss team members' strengths and weaknesses


C.

Establish rules and regulations for team members with consequences if the goals are not reached


D.

Establish team behavior and develop an understating of how to work together


Expert Solution
Questions # 469:

A project manager finds out that the required project status reports have not been

filled out by most team members. These status reports are urgently needed to compile a

comprehensive status report for the project sponsor.

What should the project manager do to address this situation?

Options:

A.

Reprimand the team members who did not fill out the status reports.


B.

Justify the team members' behavior to the project sponsor.


C.

Quickly put together a report that will satisfy the project sponsor.


D.

Discuss the issue with the team members at fault.


Expert Solution
Questions # 470:

A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.

What should the project manager do?

Options:

A.

Suggest an agile approach to refine these requirements and prioritize them according to the project objectives


B.

Validate the prioritization of all requirements with the sponsor and share the results with the stakeholders


C.

Review the project governance to validate the policies procedures and guidelines used to prioritize the project


D.

Ask the stakeholders to refine these requirements at a level of detail that becomes more stable and measurable


Expert Solution
Questions # 471:

A developer who has almost completed a required product feature for a prototype

leaves the company in the middle of an iteration. What should the project manager do?

Options:

A.

Review the backlog to reschedule the deliverable for a later iteration.


B.

Engage with stakeholders directly to review the iteration process.


C.

Determine whether other cross-functional team members are able to take over the

work.


D.

Go to management and ask to hire a new external developer.


Expert Solution
Questions # 472:

During a meeting with a customer, it was determined that participants of the meeting

had different draft versions of an important design document. What should the project

manager do first to ensure that this does not happen again?

Options:

A.

Revisit the communication process control.


B.

Ensure only the approved version is shared.


C.

Investigate how draft versions were shared.


D.

Ensure only the latest version is shared.


Expert Solution
Questions # 473:

Toward the end of a protect the project manager did not receive approval from a key stakeholder because the necessary deliverables were not functioning as expected. What should the project manager do next?

Options:

A.

Review the stakeholder engagement plan


B.

Review the quality management plan


C.

Review the requirements traceability matrix


D.

Review the work breakdown structure (WBS)


Expert Solution
Questions # 474:

A complex, high-value agile project includes sprint demonstrations with the customer

every four weeks. Executive management is concerned about the project's progress and

wants more frequent updates on the project status.

What should the project manager do?

Options:

A.

Inform executive management that the customer is made aware of the status during

the sprint demo.


B.

Prepare a weekly status report and share it with executive management every week.


C.

Inform executive management about agile principles and processes that are followed

in the project.


D.

Ask the team to prepare and share the status report with executive management every

week.


Expert Solution
Questions # 475:

A project manager has been assigned with initiating a large project to deliver

complex equipment. Part of the project will be the result of a long research process, but once

this is completed, the other part of the project must be incrementally delivered to the

customer.

Which approach should the project manager choose for this project?

Options:

A.

Agile


B.

Waterfall


C.

Predictive


D.

Hybrid


Expert Solution
Questions # 476:

During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?

Options:

A.

Let the product go to market and wait for customer feedback regarding quality


B.

Ask the quality manager to include the final user tests in the quality management plan.


C.

Submit a change request to analyze a new set of quality tests


D.

Ask the product manager to include the final user tests in the quality management plan


Expert Solution
Questions # 477:

A project manager is leading a project that is on time and under budget. In the

weekly meeting with the team, the project manager finds out that one of the tasks due next

week does not have an assigned resource available for it. The resource is currently assigned

to another project.

What should the project manager do to manage the situation?

Options:

A.

Ask the procurement department to supply a different resource.


B.

Change the schedule according to the availability of the resource.


C.

Ask the sponsor to obtain the resource as originally planned.


D.

Contact the other project manager to request the resource.


Expert Solution
Questions # 478:

A project manager submits several requests to purchase required hardware and

knows from previous experience that this kind of procurement usually results in disputes

between the company and its suppliers. How can the project manager mitigate this risk in the

request for proposal (RFP) with suppliers?

Options:

A.

Ask the legal team to review the RFP.


B.

Ask the project team to submit the RFP.


C.

Request approval of the RFP from the project sponsor.


D.

Request approval of the RFP from management.


Expert Solution
Questions # 479:

An agile project manager is evaluating the method that will be used to display the

value of the work performed to date. Which method will they select to display to the project stakeholder?

Question # 479


Expert Solution
Questions # 480:

A company made several changes recently, which resulted in a positive change in

the company culture. A project manager was just assigned to report to a new project

supervisor whose leadership style is about getting things done quickly regardless of employee

and operational impacts. Some employees are complaining about this.

What should the project manager do?

Options:

A.

Clarify expectations by explaining the company culture with the supervisor.


B.

Ask senior management to move the supervisor to a different project.


C.

Revisit the company's organizational culture.


D.

Instruct the employees to listen to the supervisor.


Expert Solution
Questions # 481:

A project manager has been assigned to a project that is in progress. The project

manager is looking for information regarding why the project is being completed.

What should the project manager do first?

Options:

A.

Evaluate the project exit criteria in the project charter.


B.

Reach out to the senior executive sponsor for the project.


C.

Understand the project success criteria and objectives.


D.

Review the project status reporting for the latest information.


Expert Solution
Questions # 482:

A subcontractor informs the project manager that they are unable to supply a key

component to the project. What should the project manager do?

Options:

A.

Discuss the issue with the project sponsor and request extra time and budget to obtain

the component from a different supplier.


B.

Raise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response


C.

Submit a change request to the change control board (CCB) for changes to the

performance measurement baseline to obtain the component from a different supplier.


D.

Raise a new issue in the issue log and convene subject matter experts (SMEs) and

relevant stakeholders to identify alternatives to address the problem.


Expert Solution
Questions # 483:

A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person

What should the project manager do first?

Options:

A.

Request additional developers to join the project team through the change cannot process


B.

Break down the deliverable by using the work breakdown structure (WBS) process to make it more manageable for task assignment


C.

Assign the entire deliverable to the first available developer to lead and have them assign the work to the remaining developers


D.

Include the situation as a risk in the risk register identify risk impacts and possible mitigations, and monitor closely


Expert Solution
Questions # 484:

During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?

Options:

A.

Add the stakeholder details into the periodic reports and update the project management plan


B.

Invite the stakeholder to all future project review meetings and update the project management plan


C.

Update the project management plan with the new information and inform all of the relevant stakeholders


D.

Meet with the stakeholder to better understand their expectations and update the stakeholder engagement plan


Expert Solution
Questions # 485:

A project manager notices that the response action for an identified issue is insufficient for solving the problem What should the project manager do next?

Options:

A.

Include the issue in the risk register and update the team


B.

Document the continuing issue and failed solution


C.

Inform the stakeholders about the failure and update the issue log


D.

Meet with the project team to find another solution


Expert Solution
Questions # 486:

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

Options:

A.

Update the project management plan in order to get back on track.


B.

Ensure the team receives continuous feedback from customers users.


C.

Submit a change request to adjust the project scope.


D.

Ensure the team understands all additional project requirements.


Expert Solution
Questions # 487:

A project leader is assigned to a new project and is asked to assemble an effective

five-member agile team. If the project leader has no restrictions, which team should they

choose?

Options:

A.

A team whose members work independently and are the best subject matter experts

(SMES)


B.

A team whose members have more general aptitudes but like to work individually


C.

A team whose members have different skill sets and are spread out geographically


D.

A team whose members have more general aptitudes and can collaborate on different tasks


Expert Solution
Questions # 488:

A company has always acquired very specialized services from local companies for

its projects. During the planning stage for a regulatory project, the project manager is informed

that local vendors would not be able to operate due to an unexpected major event. There is an

option to hire the same services from companies in other countries.

What should the project manager do in this situation?

Options:

A.

Plan to execute the procurement tasks in a virtual environment.


B.

Review organizational process assets (OPAs) for similar projects.


C.

Create a change request to extend the duration of the project.


D.

Ask the project sponsor to put the project on hold.


Expert Solution
Questions # 489:

A team member is openly criticized by others during a standup meeting for failing to

complete yesterday's tasks. What should the agile coach do first to address the situation?

Options:

A.

Emphasize the ground rules and then focus on today's activities and impediments.


B.

Let the discussion go on as it is important that the team is clear on priorities for the

day.


C.

Address the team members involved during the next sprint retrospective.


D.

Avoid the discussion by referring to the team charter.


Expert Solution
Questions # 490:

A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.

What should the project manager do to address the concem9

Options:

A.

Provide team-building activities so that the team can learn how to overcome disruptive behavior


B.

Inform the disruptive team member's functional manager that the disruptive behavior should be stopped immediately


C.

Request a meeting with the disruptive team member and help to resolve the issue


D.

Encourage self-governance and ask the concerned team member to speak to the disruptive team member directly


Expert Solution
Questions # 491:

Throughout an entire project, the project manager took notes at every meeting with

team members. These notes provided useful insights from key stakeholders, which later

resulted in increased value to the project. The project manager thought it would be helpful to

keep these notes as a future reference for other project managers within the organization.

Where should the notes be located?

Options:

A.

Lessons learned


B.

Organizational process assets (OPAs)


C.

Enterprise environmental factors (EEFs)


D.

Project management plan


Expert Solution
Questions # 492:

A project team has transitioned to full-time remote working. The project manager

started noticing that some team members have not been completing their assigned tasks by

the planned dates despite reminders during weekly team meetings. This has the potential for

delaying the project delivery.

How should the project manager resolve this situation?

Options:

A.

Communicate the delivery dates twice a week to the team members to ensure timely

delivery.


B.

Set up review sessions with each of the team members to identify the root cause of

delays.


C.

Mentor the team members to work in a remote work environment to ensure

productivity.


D.

Talk to the resource managers regarding the delay and request additional resources


Expert Solution
Questions # 493:

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

Options:

A.

Motivate the team and deploy the necessary resources.


B.

Find a way to maintain the project schedule.


C.

Impose authority on the project.


D.

Request additional resources from the sponsor and motivate the team.


Expert Solution
Questions # 494:

A project manager is assigned to a new water treatment plant project that has been

delayed for many years. It is revealed in the project charter that the sponsors of this project

are from three different business units. This is the first time the sponsors have ever

implemented such a project.

What should the project manager do?

Options:

A.

Establish mentoring and coaching sessions.


B.

Review the knowledge repository for similar projects.


C.

Schedule the project kick-off meeting immediately.


D.

Meet with the project sponsors to align expectations


Expert Solution
Questions # 495:

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

Options:

A.

Review the work allocation and reassign some tasks to shorten the critical path.


B.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.


C.

Ask the team members to work overtime to finish the tasks on time according to the schedule.


D.

Keep the task assignments unchanged since the project management plan has been approved.


Expert Solution
Questions # 496:

The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.

What strategy should the project manager use in order to keep delivering value in a restricted environment?

Options:

A.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.


B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance.


C.

Restrict the project scope only to basic critical features, and run the project with the current staffing level until all of the budget is consumed.


D.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction


Expert Solution
Questions # 497:

A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.

How should the project manager address this issue?

Options:

A.

Modify the daily standup meetings to include project status reporting.


B.

Escalate the issue to the change control board (CCB) and ask for advice.


C.

Adopt the role of supporting and empowering the project team to do the work.


D.

Change the approach for the project to a predictive approach.


Expert Solution
Questions # 498:

An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance

team is requesting a project budget for the new product.

What should the team do to address this request?

Options:

A.

Work with the finance team to transition to incremental budgeting.


B.

Request the finance team to allocate a budget based on historical data.


C.

Provide the budget to the finance team for only the planned increments.


D.

Extrapolate the budget based on the current cost performance index (CPI).


Expert Solution
Questions # 499:

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area

What should the project manager do first?

Options:

A.

Identify an alternative site.


B.

Update the issue log


C.

Issue a change request


D.

Update the risk register.


Expert Solution
Questions # 500:

At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.

How should the project manager proceed?

Options:

A.

Stop the meeting and reschedule for another time with a more concise presentation.


B.

Set up information review sessions before reconvening another approval session.


C.

Get approval and promise to email more information to the stakeholders to clarify the technical details.


D.

Obtain approval as fast as possible and close the meeting.


Expert Solution