Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 497 Topic 50 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 497 Topic 50 Discussion

PMP Exam Topic 50 Question 497 Discussion:
Question #: 497
Topic #: 50

A project manager was notified about a new regulatory requirement that could impact the project schedule.

What should the project manager do first?


A.

Increase the amount of slack in the critical path to reduce the impact of the regulatory requirement.


B.

Update the schedule and project risk register according to the regulatory requirement.


C.

Consult the project management plan for guidance on addressing the regulatory requirement.


D.

Assess the impact of implementing the potential regulatory requirement on the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.