PMI Project Management Professional (2025 Version) PMP Question # 497 Topic 50 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 497 Topic 50 Discussion

PMP Exam Topic 50 Question 497 Discussion:
Question #: 497
Topic #: 50

A new privacy law will go into effect at the beginning of the next calendar year. The project manager realizes the project needs to be compliant with the new law. What should the project manager do next?


A.

Inform the project steering committee of this constraint.


B.

Inform the project team and create a spike for the next Iteration.


C.

Inform the legal department that the project scope will be updated.


D.

Inform the product owner that the project will continue as planned.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.