Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 495 Topic 50 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 495 Topic 50 Discussion

PMP Exam Topic 50 Question 495 Discussion:
Question #: 495
Topic #: 50

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?


A.

Ensure that customer requirements do not change from the start of the project.


B.

Ensure that the definition of done (DoD) is well defined and complete for future iterations.


C.

Ensure that the development and quality assurance team members implement the feature correctly.


D.

Ensure that the team facilitator allocates tasks correctly to team members.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.