PMI Project Management Professional (2025 Version) PMP Question # 496 Topic 50 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 496 Topic 50 Discussion

PMP Exam Topic 50 Question 496 Discussion:
Question #: 496
Topic #: 50

A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation

What should the project manager do next?


A.

Document the issue in the issue log and escalate to the project sponsor


B.

Inform the project sponsor and suggest canceling the project


C.

Review the project goals and eat criteria m the project charter


D.

Ask the leader of research and development to decide on next steps


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.