The start of a 12-month project has been delayed by 2 months The project has a fixed budget, deadline and product specifications. What should the project manager do next?


A.

Schedule a time to negotiate a trade-off regarding the quality of the product with the customer


B.

Meet with the risk manager to identify potential threats related to the schedule delay.


C.

Set up a meeting with the project sponsor and submit a change request to the scope of the product


D.

Start the project plan for the scope and quality and identify options to deliver and meet stakeholders expectations