Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 500 Topic 51 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 500 Topic 51 Discussion

PMP Exam Topic 51 Question 500 Discussion:
Question #: 500
Topic #: 51

For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product

After collecting the new requirements, what should the project manager do?


A.

Assess the impact of the new requirements and initiate the change request process.


B.

Work with the product manager and the rest of the team to update the project backlog.


C.

Assess the impact and communicate the updated product roadmap to the stakeholders.


D.

Follow the change management plan to update the risk register so It accounts for the added scope.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.