Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 499 Topic 50 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 499 Topic 50 Discussion

PMP Exam Topic 50 Question 499 Discussion:
Question #: 499
Topic #: 50

A project is 20% complete. The client has accepted a project order amendment that involves a major change. Without this major change, the project result will be useless for the client organization.

What should the project manager do?


A.

Update the project status from "active" to "on hold" until there is more clarity on the scope of the change.


B.

Initiate planning for the project with the modified scope as laid out in the client's purchase order.


C.

Set up a meeting with the client and the project team to identify ways to safeguard the project from the change.


D.

Consult the project sponsor to understand if the change must be processed for project execution.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.