PMI Project Management Professional (2025 Version) PMP Question # 499 Topic 50 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 499 Topic 50 Discussion

PMP Exam Topic 50 Question 499 Discussion:
Question #: 499
Topic #: 50

An engineer working on a project team has tasks that require an additional skill that the engineer does not have a designer on the team is experienced with this skill from previous jobs and is willing to teach this skill even though it is not part of the current work

What should the project manager do?


A.

Escalate the situation to the engineer's manager


B.

Request external training for the engineer


C.

Request external training for the engineer and designer


D.

Allow the engineer and designer to cross-train with each other


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.