Question #: 498
Topic #: 50

A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.

What should the newly assigned project manager do first to understand the issues?


A.

Escalate the issues to the project sponsor.


B.

Review the issues log to ensure the issues are captured.


C.

Check the risk management plan to ensure there is a strategy to address the issues.


D.

Ask the key stakeholders to discuss the issues with the project team.