Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 457 Topic 46 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 457 Topic 46 Discussion

PMP Exam Topic 46 Question 457 Discussion:
Question #: 457
Topic #: 46

A stakeholder is requesting that the project manager share project status updates

on a regular basis. This stakeholder is not included in the regular distribution list.

What should the project manager do?


A.

Start sending status updates to this stakeholder based on the request.


B.

Ask the stakeholder's manager if the stakeholder can be added to the list.


C.

Review the stakeholder engagement and communications management plans.


D.

Escalate the stakeholder’s request to the project sponsor.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.