A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.
Which risk management process should be performed?
A.
Plan Risk Responses, to outline the possible options to bypass the system performance issue
B.
Perform Qualitative Risk Analysis, to assess the extent of the system performance impact
C.
Monitor Risks, to install system performance monitoring tools and update the risk register
D.
Perform Quantitative Risk Analysis, to outline the details of the system performance issues
When a defect is identified during user acceptance testing that could significantly impact the system’s performance, and the project team advises that this defect puts the delivery date at risk, the appropriate risk management process to perform is Plan Risk Responses. This process involves developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks. The aim is to determine how to approach, plan, and execute the risk management activities for a project1.
[: Plan Risk Responses for Your Projects - Project Management Academy1., , ]
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit