PMI Project Management Professional (2025 Version) PMP Question # 457 Topic 46 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 457 Topic 46 Discussion

PMP Exam Topic 46 Question 457 Discussion:
Question #: 457
Topic #: 46

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?


A.

Plan Risk Responses, to outline the possible options to bypass the system performance issue


B.

Perform Qualitative Risk Analysis, to assess the extent of the system performance impact


C.

Monitor Risks, to install system performance monitoring tools and update the risk register


D.

Perform Quantitative Risk Analysis, to outline the details of the system performance issues


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.