PMI Project Management Professional (2025 Version) PMP Question # 476 Topic 48 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 476 Topic 48 Discussion

PMP Exam Topic 48 Question 476 Discussion:
Question #: 476
Topic #: 48

A project manager is leading a hybrid project. The self-organizing teams are

continually late in delivering their demos, resulting in low morale. The steering committee is

familiar with the reporting and planning associated with a predictive approach and is

concerned about the project because it is unclear if the expected value will be delivered.

What should the project manager do?


A.

Emphasize to the teams the importance of reaching the agreed deadlines and value.


B.

Request to coach the team to ensure motivated project team members are on board.


C.

Update the project schedule with a buffer to reflect the expected delays being incurred

by the team.


D.

Suggest to the teams to limit the scope of work per iteration so they will start to deliver

more reliably.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.