Question #: 476
Topic #: 48

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant

business value. What should the project manager do?


A.

Call the stakeholder to tell them that the final product schedule must be extended due to this last minute, urgent request.


B.

Perform an impact analysis and share the overall schedule impact before deciding on a new priority.


C.

Reject the new requirement from the sponsor as this is going to impact the delivery of the stakeholder's final product.


D.

Ask the product owner to prioritize the new request from the sponsor and ask the team to work on it immediately.