Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 477 Topic 48 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 477 Topic 48 Discussion

PMP Exam Topic 48 Question 477 Discussion:
Question #: 477
Topic #: 48

Customers are concerned about the quality of an interim software system for a project. The quality control team has approved the software, but the customers are complaining that some functions do not comply with the requirements.

What should the project manager do to prevent this from happening again?


A.

Review the risk impact of quality nonconformance.


B.

Review the communications management plan.


C.

Revise the quality management plan.


D.

Revise the product acceptance specifications.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.