PMI Project Management Professional (2025 Version) PMP Question # 477 Topic 48 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 477 Topic 48 Discussion

PMP Exam Topic 48 Question 477 Discussion:
Question #: 477
Topic #: 48

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?


A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics


B.

Stop the project and kick off another project to apply alternative wires for the machine


C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider


D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.