Question #: 477
Topic #: 48

A project manager Is transitioning from a predictive We cycle project to a new agile project How should the project manager manage and control the scope for the new project?


A.

Create a scope baseline and put the rest as backlog activities.


B.

Estimate the work the team can complete and define story sizes to keep the project under control.


C.

Develop a plan to complete more work In less time.


D.

Spend a short amount of time defining the scope and building prototypes to refine the requirements.