PMI Project Management Professional (2025 Version) PMP Question # 479 Topic 48 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 479 Topic 48 Discussion

PMP Exam Topic 48 Question 479 Discussion:
Question #: 479
Topic #: 48

A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.

Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)


A.

Organizational process assets (OPAs)


B.

Lesson learned registers from past projects


C.

Historical issue logs


D.

Project scope statement


E.

Project management plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.