PMI Project Management Professional (2025 Version) PMP Question # 478 Topic 48 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 478 Topic 48 Discussion

PMP Exam Topic 48 Question 478 Discussion:
Question #: 478
Topic #: 48

A project manager submits several requests to purchase required hardware and

knows from previous experience that this kind of procurement usually results in disputes

between the company and its suppliers. How can the project manager mitigate this risk in the

request for proposal (RFP) with suppliers?


A.

Ask the legal team to review the RFP.


B.

Ask the project team to submit the RFP.


C.

Request approval of the RFP from the project sponsor.


D.

Request approval of the RFP from management.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.