Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 478 Topic 48 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 478 Topic 48 Discussion

PMP Exam Topic 48 Question 478 Discussion:
Question #: 478
Topic #: 48

A project team is conducting a retrospective. The team wants to identify what had

a positive impact on the velocity and keep doing it.

Click on the area that the team should focus on to identify good practices.

PMP Question 478


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.