Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 481 Topic 49 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 481 Topic 49 Discussion

PMP Exam Topic 49 Question 481 Discussion:
Question #: 481
Topic #: 49

The project team members have finalized the technical specifications after their discussion with the machine manufacturers. However, it has been identified that the specifications are not aligned with the project management office (PMO). The project team members are confident about their choice of specifications.

What should the project manager do in this situation?


A.

Request a decision from the project sponsor.


B.

Give approval of the technical specifications.


C.

Ask the sponsor for additional funding to hire a senior subject matter expert (SME).


D.

Schedule a meeting with all of the subject matter experts (SMEs) to discuss.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.