Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 480 Topic 49 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 480 Topic 49 Discussion

PMP Exam Topic 49 Question 480 Discussion:
Question #: 480
Topic #: 49

A specialized team member has just received news that they must leave the office for several weeks They have approximately two workdays until they will leave and then they will become unavailable through any communication channels. There is a key deadline approaching

What should the agile project manager do?


A.

Ask the team member to complete as much as they can now.


B.

Ask the team member to work with their peers to knowledge share


C.

Ask the team member to identify their specialist tasks


D.

Ask the team member to host a special team meeting.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.