us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?
A.
Review project cost because the project is over budget and ahead of schedule
B.
Review project schedule and cost because the project is over budget and behind schedule
C.
Review project schedule because the project is under budget and behind schedule
D.
Review project scope because the project is under budget and ahead of schedule
The graph shows that the project is performing below the baseline for both schedule and cost, which means it is behind schedule and under budget. This indicates that the project is not meeting its planned progress and deliverables, and may have some issues with scope, quality, or resources. The project manager should review the project schedule to identify the root causes of the delays, and take corrective actions to bring the project back on track. The project manager should also monitor the project cost to ensure that it does not exceed the budget, and communicate the status and changes to the stakeholders. References:
PMBOK Guide, 7th Edition, Chapter 8: Performance Measurement and Reporting1
The PMI Guide to Business Analysis, Chapter 5: Planning Business Analysis Work2
Business Analysis for Practitioners: A Practice Guide, Chapter 4: Elicitation and Collaboration3
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit