PMI Project Management Professional (2025 Version) PMP Question # 480 Topic 49 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 480 Topic 49 Discussion

PMP Exam Topic 49 Question 480 Discussion:
Question #: 480
Topic #: 49

us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?


A.

Review project cost because the project is over budget and ahead of schedule


B.

Review project schedule and cost because the project is over budget and behind schedule


C.

Review project schedule because the project is under budget and behind schedule


D.

Review project scope because the project is under budget and ahead of schedule


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.