PMI Project Management Professional (2025 Version) PMP Question # 482 Topic 49 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 482 Topic 49 Discussion

PMP Exam Topic 49 Question 482 Discussion:
Question #: 482
Topic #: 49

During the executing phase, a project manager is reviewing the issue log and finds

there are outstanding high-priority issues that are still open. Most of the open issues require

effort from external domain experts who are not on the project team.

What should the project manager do?


A.

Ask the issue reporter to close the issues, because there are no project team members

who have the required domain knowledge.


B.

Review the open issues with the issue reporter and issue a change request to hire an

external domain expert.


C.

Request that the project team members learn the required domain knowledge and

resolve the open issues in a short time.


D.

Reduce the project scope to ensure that the project team has the knowledge to deliver

the system on schedule.