Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 460 Topic 47 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 460 Topic 47 Discussion

PMP Exam Topic 47 Question 460 Discussion:
Question #: 460
Topic #: 47

A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.

What should the project manager do?


A.

Seek help from the project sponsor to get an SME from another team in the organization.


B.

Provide an opportunity to one of the existing team members to become an SME.


C.

Hire a contractor from outside of the organization to continue with the project.


D.

Ask team members to document the issue and address it in the next project meeting.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.