PMI Project Management Professional (2025 Version) PMP Question # 460 Topic 47 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 460 Topic 47 Discussion

PMP Exam Topic 47 Question 460 Discussion:
Question #: 460
Topic #: 47

A project manager is working with a team that is new to agile. One of the more

influential stakeholders struggles with the nature of agile. The project manager knows that this

stakeholder is needed as an advocate and wants to do everything possible to make the

stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project's

performance?


A.

Results of the MoSCoW assessment


B.

Cost-benefit analysis


C.

Return on investment (ROI) analysis


D.

Earned value analysis (EVA)


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.