Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 461 Topic 47 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 461 Topic 47 Discussion

PMP Exam Topic 47 Question 461 Discussion:
Question #: 461
Topic #: 47

During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.

What should the project manager do next?


A.

Discuss approval of the change request in the next project meeting


B.

Perform a risk assessment on the required change request.


C.

Evaluate the change request against the project scope statement


D.

Ask the sponsor for more funds to cover the change request


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.