Question #: 461
Topic #: 47

At the end of a project, one of the suppliers is facing financial difficulties and is

pushing the project manager to obtain financial, legal, and administrative approval in order to

communicate formal project closure and ensure the transfer of liability. What should the

project manager do next?


A.

Compare the achieved results to the contract requirements.


B.

Make the final payment as the project is completed.


C.

Transfer the remaining variances and close the project.


D.

Escalate to higher management to expedite the approval.