Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 468 Topic 47 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 468 Topic 47 Discussion

PMP Exam Topic 47 Question 468 Discussion:
Question #: 468
Topic #: 47

A project is delivered using a hybrid approach. In the daily meeting, one of the developers informs the team that the business that will implement the next version of the product has a new manager. There is one more sprint before the new version of the product enters the staging phase.

What should the project manager do?


A.

Invite the new manager to the next daily scrum.


B.

Invite the new manager to the next sprint review.


C.

Invite the new manager to the next sprint planning.


D.

Invite the new manager to the next sprint retrospective.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.