PMI Project Management Professional (2025 Version) PMP Question # 472 Topic 48 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 472 Topic 48 Discussion

PMP Exam Topic 48 Question 472 Discussion:
Question #: 472
Topic #: 48

A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?


A.

Document the lessons learned and implement improvements in the next sprint


B.

Facilitate a daily standup with the team to track the implementation of changes


C.

Organize a demonstration of the changes in the enterprise system


D.

Request that all team members think of ideas to improve processes.