Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 469 Topic 47 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 469 Topic 47 Discussion

PMP Exam Topic 47 Question 469 Discussion:
Question #: 469
Topic #: 47

A team member increased the estimated completion time for their activities on the critical path. This action, however, has caused friction among the team members. The project manager reviewed the key performance indicators (KPIs) that show the issue.

What should the project manager do first?


A.

Conduct a root cause analysis (RCA) and plan the correct actions to ensure completion of the tasks on time.


B.

Allocate another resource to help the team member to complete the tasks and meet the estimated activity time.


C.

Train the team member in the methodology to get the sufficient knowledge to meet the estimated activity time.


D.

Apply crashing to the strategic tasks to recover any time that was lost to bring the project on track.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.