Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 469 Topic 47 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 469 Topic 47 Discussion

PMP Exam Topic 47 Question 469 Discussion:
Question #: 469
Topic #: 47

A project manager has just been assigned to a project to build new software for a client. All the requirements have been gathered.

What should the project manager tell the team members to focus on?


A.

Reducing cost for the customer


B.

Delivering value to the customer


C.

Working together as a team


D.

Finishing the project on schedule


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.