Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 489 Topic 49 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 489 Topic 49 Discussion

PMP Exam Topic 49 Question 489 Discussion:
Question #: 489
Topic #: 49

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)


A.

Look for processes that cause bottlenecks and slow down the team's agility


B.

Assign the items with high complexity lo senior developers


C.

Empower the learn to make decisions to remove impediments


D.

Work with the team to remove impediments as quickly as possible


E.

Move the items with high complexity to the last iterations


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.