PMI Project Management Professional (2025 Version) PMP Question # 489 Topic 49 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 489 Topic 49 Discussion

PMP Exam Topic 49 Question 489 Discussion:
Question #: 489
Topic #: 49

A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder's presence has had a negative impact on the team's morale, while also impacting productivity

How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?


A.

Set up a meeting with the stakeholder to address their concerns directly


B.

Move to a predictive design-and-requirements gathering approach


C.

Talk to the team separately to address the stakeholder's concerns


D.

Schedule a team retrospective and invite the stakeholder


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.