New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 494 Topic 50 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 494 Topic 50 Discussion

PMP Exam Topic 50 Question 494 Discussion:
Question #: 494
Topic #: 50

A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?


A.

Request the team member to move to another team.


B.

Delegate other team members to complete this team member's tasks.


C.

Mentor the team member and provide the necessary training.


D.

Include this team member in an improvement program through a human resources request.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.