A project manager notices that the response action for an identified issue is insufficient for solving the problem What should the project manager do next?
A.
Include the issue in the risk register and update the team
B.
Document the continuing issue and failed solution
C.
Inform the stakeholders about the failure and update the issue log
D.
Meet with the project team to find another solution
When a project manager identifies that the response action for an issue is insufficient, it is crucial to take immediate action to prevent further complications. The best course of action in this scenario is to meet with the project team to find another solution1. This approach ensures that all team members are aware of the issue and can contribute their expertise and ideas to resolving it. It also promotes transparency and collaboration within the team1. The other options (A, B, C) are also important steps in issue management, but they are not the immediate next steps when a response action has proven to be insufficient2. References: 12
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit