Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 492 Topic 50 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 492 Topic 50 Discussion

PMP Exam Topic 50 Question 492 Discussion:
Question #: 492
Topic #: 50

A project manager is preparing a large and complex international project. In order for the team to work well together in a virtual environment, the project manager needs to set up ground rules for good communication.

What should the project manager do first?


A.

Establish a communication channel.


B.

Create a communication protocol.


C.

Develop the stakeholder analysis.


D.

Distribute the risk register.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.