PMI Project Management Professional (2025 Version) PMP Question # 492 Topic 50 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 492 Topic 50 Discussion

PMP Exam Topic 50 Question 492 Discussion:
Question #: 492
Topic #: 50

In an ongoing project, stakeholders have been approaching team members for status

reports and changes without consulting the project manager. What should the project

manager do to ensure a successful project?


A.

Send the project charter to all stakeholders for information.


B.

Send an email to all stakeholders directing them to approach the project manager

directly.


C.

Review the stakeholder engagement plan and inform the stakeholders.


D.

Review the change management plan and ask the change control board (CCB) to be

involved.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.