Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 491 Topic 50 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 491 Topic 50 Discussion

PMP Exam Topic 50 Question 491 Discussion:
Question #: 491
Topic #: 50

A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?


A.

Propose a solution redesign for the project


B.

Perform risk analysis against the issue.


C.

Revise the project's quality control measurements


D.

Develop a mitigation based on the solution design


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.