Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 490 Topic 50 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 490 Topic 50 Discussion

PMP Exam Topic 50 Question 490 Discussion:
Question #: 490
Topic #: 50

During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.

How should the project manager properly address this situation?


A.

Align the project goals with the team member.


B.

Reassign the team member to another project.


C.

Nominate the team member to receive agile training.


D.

Allocate another resource to support the team member.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.