PMI Project Management Professional (2025 Version) PMP Question # 490 Topic 50 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 490 Topic 50 Discussion

PMP Exam Topic 50 Question 490 Discussion:
Question #: 490
Topic #: 50

During the forming phase of a project team a project manager implements several team-building initiatives and decides it would be fun to have improvisations theater activities. After the sessions the project manager received feedback from some key team members who felt that although the activity was fun it was not appropriate for the purpose of team building.

What should the project manager have done to avoid this negative feedback'?


A.

Assessed and analyzed personality indicators from the project team


B.

Sent the activity details to everyone involved prior to the session


C.

Communicated the decision to conduct this activity to the key team stakeholders


D.

Selected a vendor for the activity according to the procurement management plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.