PMI Project Management Professional (2025 Version) PMP Question # 487 Topic 49 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 487 Topic 49 Discussion

PMP Exam Topic 49 Question 487 Discussion:
Question #: 487
Topic #: 49

A key project stakeholder does not attend any of the project meetings and is

providing false information that the project team is not delivering on time. What should the

project manager do to address this situation?


A.

Create a new communication artifact for the key stakeholder.


B.

Email the latest status report to the key stakeholder.


C.

Share the meeting recordings with the key stakeholder.


D.

Discuss communication needs with the key stakeholder.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.