Question #: 488
Topic #: 49

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?


A.

Document the risk register in the project charter.


B.

Speak to the customer and add the issue to the issue log.


C.

Review user roles and update the team charter.


D.

Involve the product owner to rewrite the user stories.