Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 486 Topic 49 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 486 Topic 49 Discussion

PMP Exam Topic 49 Question 486 Discussion:
Question #: 486
Topic #: 49

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.

What should the project manager do next?


A.

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.


B.

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.


C.

Address this concern with the functional managers to ensure there will be no further delays.


D.

Schedule a meeting with all of the functional managers to resolve the resource conflicts.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.