Question #: 485
Topic #: 49

A project manager is leading a diverse project team that includes new and experienced team members. A conflict has occurred between two team members. One team member prefers using digital tools for project communication. The other team member prefers in-person meetings and phone calls for communication.

What should the project manager do to manage this conflict?


A.

Arrange a team-building activity to foster understanding and open communication among the team members.


B.

Allow the team members to continue using their preferred communication tools and methods.


C.

Initiate a conversation with the team members individually to understand their situations regarding communication.


D.

Instruct the team members to adapt to the project's communication tools and methods.