PMP Exam Topic 49 Question 483 Discussion:
Question #: 483
Topic #: 49

At the end of a project, the project manager is asked to submit project documentation for an internal audit in response to regulatory requirements. What should the project manager have done at the beginning of the project to ensure that project documentation would

fulfill these requirements?


A.

Conducted a document review


B.

Confirmed documentation requirements with stakeholders


C.

Updated the project templates


D.

Implemented a new change control policy