Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 483 Topic 49 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 483 Topic 49 Discussion

PMP Exam Topic 49 Question 483 Discussion:
Question #: 483
Topic #: 49

The team's velocity is inconsistent, leading the product owner to believe the team is creating too many points in their user stories.

What should the scrum master do first?


A.

Remind the product owner that their role is to determine what the team should work on during the iteration.


B.

Meet with the product owner for planning and to resize the stories in the backlog.


C.

Invite the product owner to planning poker meetings and get their approval after each story is sized.


D.

Raise this concern with the team and review the performance of the past three sprints.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.