Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 473 Topic 48 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 473 Topic 48 Discussion

PMP Exam Topic 48 Question 473 Discussion:
Question #: 473
Topic #: 48

An organization is undergoing an agile transformation and migrating most of its projects from a predictive approach. The CFO expressed a concern that predictability on both costs and scope will be lost with the new agile approach.

What should the project manager do?


A.

Provide mentoring to the CFO, who is a key stakeholder in the project, and clarify the benefits of an agile approach.


B.

Ask the CEO to intervene by asking for support from the executive board to accelerate the company's transformation.


C.

Apply influence with other key stakeholders on the board to mitigate any risks that may be generated by the CFO's position on the matter.


D.

Submit a report to all key stakeholders on the cost-benefit analysis of the new approach and detail how the company will save money.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.