PMI Project Management Professional (2025 Version) PMP Question # 473 Topic 48 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 473 Topic 48 Discussion

PMP Exam Topic 48 Question 473 Discussion:
Question #: 473
Topic #: 48

A project has recently Kicked off. The project manager observes that thete are different expectations among the project team members. These growing misunderstandings are affecting team productivity.

Which document should the project managefve?


A.

Project charter


B.

Stakeholder register


C.

Team charter


D.

Project organization charts


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.