Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 473 Topic 48 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 473 Topic 48 Discussion

PMP Exam Topic 48 Question 473 Discussion:
Question #: 473
Topic #: 48

A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.

What immediate action should the project manager take to improve the situation?


A.

Communicate this issue to the human resources department.


B.

Provide additional training to the new hire.


C.

Increase team cohesiveness by sharing information and experiences openly.


D.

Update the issue log and define the mitigation strategy.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.