Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 474 Topic 48 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 474 Topic 48 Discussion

PMP Exam Topic 48 Question 474 Discussion:
Question #: 474
Topic #: 48

After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?


A.

Comply with the project sponsor's request to not archive the project artifacts.


B.

Document the project sponsor's instructions as the archived project artifacts.


C.

Archive the project artifacts on the project manager's local computer for future reference


D.

Consult with the project management office (PMO) for guidance on project artifacts.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.