Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 470 Topic 48 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 470 Topic 48 Discussion

PMP Exam Topic 48 Question 470 Discussion:
Question #: 470
Topic #: 48

Due to scope changes, some of the risks identified during the initiation phase have materialized into issues. What should the project manager do next?


A.

Submit a request to access contingency reserves and accept the changes.


B.

Submit a change request for additional resources and accept the changes.


C.

Ask the project sponsor to reject high-risk scope changes.


D.

Closely monitor scope changes and implement corrective actions.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.