PMI Project Management Professional (2025 Version) PMP Question # 470 Topic 48 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 470 Topic 48 Discussion

PMP Exam Topic 48 Question 470 Discussion:
Question #: 470
Topic #: 48

A project manager is leading an automation project. The project team is colocated

and includes people from both the technical and business units. The project manager

discovers that personal differences and work styles are affecting the project negatively.

How should the project manager address this?


A.

Develop a schedule that ensures people with personal differences work separately.


B.

Use an approach to the project that does not involve colocation.


C.

Meet with the team and agree on expectations from team members.


D.

Invite the functional managers of the different units to address their personal differences.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.