New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 451 Topic 46 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 451 Topic 46 Discussion

PMP Exam Topic 46 Question 451 Discussion:
Question #: 451
Topic #: 46

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?


A.

Escalate the issue to the project sponsor.


B.

Review the stakeholder engagement plan.


C.

Update the issue log.


D.

Neutralize the negative stakeholders.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.