Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 451 Topic 46 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 451 Topic 46 Discussion

PMP Exam Topic 46 Question 451 Discussion:
Question #: 451
Topic #: 46

A client is structured as a matrix organization for an agile project The project manager is working on-site with key stakeholders from different parts of the organization

How should the project manager handle the different stakeholders?


A.

All stakeholders are important, so the project manager should follow directions provided by management and key stakeholders


B.

Because there are different perspectives perform a stakeholder analysis and act based on the outcome.


C.

The project manager is working on the client's premises, so follow the directions of all the key stakeholders


D.

This is an agile project, so listen only to the directions of the project manager's supervisor and the functional managers of the organization


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.