Question #: 452
Topic #: 46

A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a

predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams

are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current

impediments.

What should the project manager do?


A.

Ask the members to be more proactive and share ideas with each other.


B.

Set up a daily virtual meeting with the development team.


C.

Plan a monthly virtual meeting to align and to review the plans.


D.

Review the issue with the project sponsor and ask for support.