PMI Project Management Professional (2025 Version) PMP Question # 453 Topic 46 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 453 Topic 46 Discussion

PMP Exam Topic 46 Question 453 Discussion:
Question #: 453
Topic #: 46

The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team

Which two actions should the project manager take? (Choose two)


A.

Review the issue with project sponsor and submit a change request


B.

Report the issue to the product manager and business segments


C.

Analyze the business benefits criteria and assumptions


D.

Discuss the issue with the operations team to assess expense overruns


E.

Schedule a project review meeting to analyze the root cause


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.