Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 453 Topic 46 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 453 Topic 46 Discussion

PMP Exam Topic 46 Question 453 Discussion:
Question #: 453
Topic #: 46

During the course of a project the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings

How should the project manager handle this?


A.

Communicate directly with the director and inform them of the communications management plan


B.

Communicate directly with the client stating that any scope changes must go through the project manager


C.

Review the stakeholder engagement plan and put in place any existing actionsaccordingly


D.

Discuss the issues with the project team and let them know that the project manager will handle scope changes


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.