PMI Project Management Professional (2025 Version) PMP Question # 453 Topic 46 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 453 Topic 46 Discussion

PMP Exam Topic 46 Question 453 Discussion:
Question #: 453
Topic #: 46

An agile project is starting its seventh out of eight iterations In a planning meeting, the team realizes that an unidentified risk became an issue and the contingency reserve has to be used.

What should the project manager do?


A.

Ask the sponsor to approve inclusion of an additional iteration to the project


B.

Ask the team to include the contingency plan in the iteration backlog


C.

Help the team review the project approach to initiate the corrective actions


D.

Ask the sponsor for money to implement the contingency plan.