PMI Project Management Professional (PMBOK 7th Version) PMP Question # 455 Topic 46 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 455 Topic 46 Discussion

PMP Exam Topic 46 Question 455 Discussion:
Question #: 455
Topic #: 46

A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) went to the client site for knowledge transfer The SMEs captured various process deviations without sharing with the project team

How can the project manager ensure knowledge transfer across the team?


A.

Ask the project team to run a deviation log review meeting with the client, highlighting that the project may not be able to go live as scheduled


B.

Ask the project management office (PMO) to provide team members with real-time visibility for deviations and facilitate team members to resolve issues


C.

Ask the SMEs to share the knowledge transfer documents with all other members by placing the documents in the project management information system (PMIS)


D.

Ask the project team to facilitate a lessons learned session during the projectclosure phase to incorporate this issue


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.