During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?
It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.
What should the project manager do?
A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.
How should the project manager proceed?
A project manager Is working on a project using a hybrid approach. The project Is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company which was approved by their functional manager
What should the project manager do first in this situation'?
A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market
How should the project manager address this issue?
A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools
In order to deliver the project successfully, what should the project manager focus on as part of the plan?
A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?
A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required
What should the project manager do?
A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.
What should the project manager do to communicate with the stakeholders?
A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.
What should the project manager do?
An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase
What should the team do next?
The project team is planning a schedule with limited information. The team |s having
issues identifying the detailed tasks and estimating task durations.
Which three techniques should the project manager use? (Choose three)
An agile project is in its early iterations, but the project manager already realizes that
more resources will be needed to achieve the expected time lines. There are no internal
resources. available.
What vendor strategy should the project manager use to maximize project delivery?
What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?
During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?
A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team
What should the project manager do?
A company is transitioning their projects to utilize hybrid project management approaches While putting together their project team, the project manager discovers the requirements from the customer are unclear and also realizes that the team members are lacking critical technical stalls needed for project success. However the customer will not accept any changes to the requirements
What should the project manager do to resolve this issue?
As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved
How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.
A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization's project management office (PMO). The project manager
believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the
technology.
What should the project manager do?
A project manager for a technology project is informed by the cybersecurity team that
there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.
What should the project manager direct the team to do?
A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.
How should the project manager handle this situation?
During a kick-off meeting at the start of project execution, the vendor presents a
migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.
What should the project manager do?
In the middle of an iteration, the product owner tells the agile team that the
government has updated legal requirements. This will result in some changes in the product
definition.
How should the project manager handle this situation?
A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline
What should the project manager do next?
The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.
What is the project manager's priority in this situation?
A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?
A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.
How should the project manager ensure the product increments deliver the anticipated requirements?
A project manager notices that one of the marketing executives in the firm always appears stressed. The project manager observes that the executive's performance is gradually declining and is affecting the project deliverables.
What should the project manager do?
A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution
phase and will affect a few key workers’ licenses, which will become noncompliant.
What should the project manager do?
Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.
What is the protect manager's first step in addressing the problem?
In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.
What should the project manager do?
At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.
What should the project manager do to start building the product faster?
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?
A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team
What should the project manager do to resolve this?
A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.
What should the project manager do moving forward?
A new solution is being deployed in countries A B and C. This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market
What should the project manager in charge of the deployment in country A do?
A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?
A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.
What should the project manager do in this scenario?
One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?
A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules
Which two actions should the project manager take with regard to schedule analysis? (Choose two)
A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor
What should the project manager have created to prevent this situation1?
A project manager for a construction site realizes the importance of stakeholder
relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.
What should the project manager do to customize the stakeholder engagement plan?
One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.
What should the project manager do?
An agile team recently started working on a project for a financial institution. The
project sponsor is concerned that an agile approach will not provide enough support for the
organization's compliance standards.
In order to mitigate this risk and avoid problems, what should the project manager do?
A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?
A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.
How should the project manager resolve this situation in their new role as servant leader?
An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?
A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project
What should the project manager do?
A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?
A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?