PMP Exam Topic 57 Question 562 Discussion:
Question #: 562
Topic #: 57

The project team is planning a schedule with limited information. The team |s having

issues identifying the detailed tasks and estimating task durations.

Which three techniques should the project manager use? (Choose three)


A.

Rolling wave planning and an adaptive approach


B.

Relative estimation to determine the task or deliverable sizes


C.

Iterations and reviews to continuously keep adapting the plan


D.

Bottom-up estimating based on a work breakdown structure (WBS)


E.

Gantt chart that includes milestones and deadlines https://www.projectmanager.com/blog/project-management/planning-techniques-for-projects