PMP Exam Topic 57 Question 563 Discussion:
Question #: 563
Topic #: 57

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?


A.

Use compression techniques to break down the scope and assign the scope pieces todifferent vendors with a fixed-price contract.


B.

Use the contingency budget for hiring additional vendor resources to mitigate any projectrisk.


C.

Engage in a time and materials (T&M) contract and hire a local vendor to supportdevelopment.


D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.