Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 563 Topic 57 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 563 Topic 57 Discussion

PMP Exam Topic 57 Question 563 Discussion:
Question #: 563
Topic #: 57

A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?


A.

Assign the feature to another team member, and have them try to complete the feature by the end of this iteration


B.

Review team capacity and reassign the functionality to additional iterations as required


C.

Determine if the team member can work from home to complete the functionality.


D.

Review the work in progress with the product owner to determine the next step


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.