Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 561 Topic 57 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 561 Topic 57 Discussion

PMP Exam Topic 57 Question 561 Discussion:
Question #: 561
Topic #: 57

A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members. How should the project manager organize the WBS?


A.

Cost oriented


B.

Deliverable oriented


C.

Customer oriented


D.

Team oriented


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.