PMI Project Management Professional (2025 Version) PMP Question # 561 Topic 57 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 561 Topic 57 Discussion

PMP Exam Topic 57 Question 561 Discussion:
Question #: 561
Topic #: 57

A senior management team member contacts an agile project lead and mentions

that certain features the senior manager thought would be in the current release were not

included. What should the agile project lead do?


A.

Assure the senior manager that these features will be queued up in the next sprint.


B.

Meet with the team to understand why the senior manager’s features were not included.


C.

Invite the senior manager to the next planning meeting.


D.

Send the product roadmap to the senior manager.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.