PMP Exam Topic 59 Question 582 Discussion:
Question #: 582
Topic #: 59

At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.

What should the project manager do to start building the product faster?


A.

Allow the sponsor to determine how long the planning phase should last.


B.

Allow the client ta determine how long the planning phase should last.


C.

Ask the functional manager to work with the team to finalize planning and begin building the product.


D.

Explain that more features can be planned in upcoming Iterations and begin building the product.