A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.
What should the project manager do moving forward?
A.
Provide clear expectations around task requirements.
B.
Review the task list with the team on a regular basis,
C.
Provide templates for the product owner to use in the future.
D.
Review the task with the sponsor to see if they are satisfied.
In project management, it is crucial for the project manager to provide clear expectations around task requirements. This ensures that all team members understand what is expected of them and can accurately report on their progress. In this scenario, the project team member reported a task as complete when it was not, indicating a possible misunderstanding of the task requirements. Therefore, moving forward, the project manager should provide clear expectations to prevent similar situations in the future. References: Project Management Professional (PMP) Reference Materials, Professional in Business Analysis Reference Materials study guide. Please note that the exact documents and page numbers are not provided as the information is based on general project management principles. For more detailed information, please refer to the specific guides and documents mentioned.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.