A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.

What should the project manager do moving forward?


A.

Provide clear expectations around task requirements.


B.

Review the task list with the team on a regular basis,


C.

Provide templates for the product owner to use in the future.


D.

Review the task with the sponsor to see if they are satisfied.