A project manager receives a request for proposal (RFP) from a client. The client

is very clear about the requirements. A requirements analysis must be done in the first

month of the project, and the client wants to see a demo of the work completed every two

weeks.

What project approach should the project manager use?


A.

Iterative for the requirements analysis and delivery phases of the project


B.

Agile for all of the phases of the project, including the requirements analysis and delivery


C.

Predictive for the requirements analysis and agile for delivery of the project


D.

Predictive for the requirements analysis and delivery phases of the project